Update Risk

You can change the risk level of a change order to record progress toward resolving the change order. Risk changes become part of the change order history and can be useful when you research and update change orders.

To update the risk level of a change order

  1. Select the change order from the Change Order List page on the Scoreboard.

    The Change Detail page appears.

  2. Select Activities, Update Risk on the menu bar.

    The Override Risk of Change Order page appears.

  3. Edit the risk value other activities fields as appropriate.

    See Activities Fields for field descriptions.

  4. Click Save.

    The risk level is updated and the activity is recorded on the Activities tab on the Change Detail page.